§ 18-304.   Conditions to be Fulfilled Prior to Connection.
No person shall make or shall cause to be made any connection of any improved property with any sewer until such person shall have fulfilled all the conditions:
      A.   Such person shall notify the Secretary of the Borough of the desire and intention to make such connection.
      B.   Such person shall pay such sewer connection fee as shall be required by the Borough as hereinafter set forth, which sewer connection fee shall be payable to the Borough.
      C.   Such person shall apply for and obtain from the Borough a permit to make such connection.
      D.   Such person shall give the Secretary of the Borough at least 24 hour notice of the time when such connection will be made, in order that the Borough, by its authorized agent, can supervise and inspect such work or connection.
(Ord. 398, 6/11/1987, §4)