Upon receipt of an application for a special permit by the Borough, the following procedures shall apply in addition to those of Part 2:
A. Within 3 working days following receipt of the application, a complete copy of the application and all accompanying documentation shall be forwarded to the County Planning Commission by registered or certified mail for its review and recommendations. Copies of the application shall also be forwarded to the Borough Planning Commission and Borough Engineer for review and comment.
B. If an application is received that is incomplete, the Borough shall notify the applicant in writing stating in what respect the application is deficient.
C. If the Borough decides to disapprove an application, it shall notify the applicant in writing of the reasons for the disapproval.
D. If the Borough approves an application, it shall file written notification, together with the application and all pertinent information, with the Department of Community and Economic Development, by registered or certified mail, within 5 working days after the date of approval.
E. Before issuing the special permit, the Borough shall allow the Department of Community and Economic Development 30 days, after receipt of the notification by the Department, to review the application and the decision made by the Borough.
F. If the Borough does not receive any communication from the Department of Community and Economic Development during the 30-day review period, it may issue a special permit to the applicant.
G. If the Department of Community and Economic Development should decide to disapprove an application, it shall notify the Borough and the applicant in writing of the reasons for the disapproval, and the Borough shall not issue the special permit.
(Ord. 582, 4/13/2009, §502; as amended by Ord. 625)