§ 154.075 STANDARDS FOR CONSTRUCTION.
   (A)   The sanitary sewers, storm sewers, drainage features, water utility mains, street improvements and electrical facilities, with all appurtenances pertaining to the above, shall be constructed and installed in each new subdivision, at the expense of the developer in accordance with the construction standards of the city.
   (B)   All construction work, such as street paving, storm sewers, curb and/or gutter work, sanitary sewers, water mains and electrical construction performed by the owner, developer or contractor, shall be subject to inspection during construction by the proper authority of the city and shall be constructed in accordance with the construction standards of the city.
   (C)   Floor level of the buildings shall be provided with a minimum of 12 inches above the top of the adjacent street curb, or street centerline, or shall be provided with drainage swale adjustment, so that the structure does not flood.
   (D)   The construction standards of the city referred to in this chapter shall be those standards approved by the City Council or, in the absence of those standards, those standards approved by the City Engineer as being in conformance with good and proper engineering standards for the type of construction in question.
(Ord. 08-358, passed 11-18-2008)