The operator, no later than six months from the effective date of the ordinance granting an initial permit, shall furnish to the Council, for approval, complete plans and specifications for the construction and operation of its system, including transmission and distribution, and provide for service to all the incorporated areas of the Village, within 30 days after receiving approval from Council, the operator must begin all the procedures to obtain whatever agreements, if any, are required from utility companies; and approvals from the Village officials required herein, After obtaining all these necessary agreements and approvals the operator shall begin construction of the system within 90 days thereafter and shall continue at such a rate as to make the service contemplated by this ordinance available to all residences in the Village within one year after commencement of construction, and available to all business establishments and other potential users in the Village within two years after commencement of construction.
(Ord. 0-1621-97, § 719.04, passed 7-21-97)