17-13-9 Submittals and procedures: public infrastructure permits
A.   Scope. An application for a public infrastructure permit requires a completed permit application, improvement plans, and all required reports and requirements defined in the town's applications, checklists, and process guides.
B.   Improvement plan requirements. Improvement plans must include all requirements defined in the town's applications, checklists, and process guides, and shall conform to all rezoning ordinances, conditions, and other applicable regulations. All plans shall be sealed by the applicable registered professional engineer licensed in the state of Arizona.
C.   Soils report. The applicant shall submit a soils report.
   1.   The report shall contain all geotechnical engineering information and recommendations applicable to the project.
   2.   The civil engineer responsible for preparing the grading plan shall incorporate all report recommendations into the plan and reference the report on the improvement plan.
   3.   Approved report recommendations shall become conditions of the permit.
   4.   The geotechnical or civil engineer shall stamp and seal the report prior to submittal.
   5.   The soils report used for the grading permit may contain the relevant information for the public infrastructure permit.
D.   Drainage report. The applicant shall submit a drainage report. The drainage report will be prepared in technical conformance with provisions of this chapter and the standards and other applicable requirements of the town. The drainage report used for the grading permit may contain the relevant information for the public infrastructure permit.
E.   At-risk work. There shall be no at-risk construction of public infrastructure.