(A) Plans approved by the city for stripping, grading, excavating, and filling work shall be maintained on site throughout the duration of the work. After EPSC measures have been installed, the permittee shall contact the city and request a preconstruction inspection.
(B) Upon completion of the preconstruction inspection and approval of EPSC measures, the EPSC permit will be issued and a grading permit may be considered.
(C) The city shall make inspections as deemed necessary to ensure the EPSC measures are being properly implemented and maintained during construction. If minimum requirements for the EPSC are not met, the permittee may be notified and enforcement actions shall be taken.
(D) The permittee or his/her agent shall make regular inspections of all control measures to determine the overall effectiveness of the EPSC plan and the need for additional control measures. The minimum frequency of these inspections shall be once every seven (7) calendar days and before and after storm events of one-half (1/2) inch of precipitation or more. All inspections shall be documented in written form and kept on the construction site. Reports should be available for the city or state inspectors to review upon request during a site inspection.
(E) The city shall be permitted to enter the property of the applicant as deemed necessary to make regular inspections to ensure the validity of the reports filed herein.
(Ord. 2006-26, passed 12-4-06)