§ 151.096 START OF CONSTRUCTION.
   (A)   Work on the proposed development shall begin within 180 days after the date of issuance of the permit or the permit shall expire unless a time extension is granted, in writing, by the Floodplain Administrator. All work on the proposed development shall be completed within 18 months of permit issuance, at which time, the permit shall expire unless a time extension is granted in writing by the Floodplain Administrator. The request for a time extension shall be in writing and shall state the reasons for the extension.
   (B)   When considering an extension, the Floodplain Administrator shall consider the following criteria.
      (1)   Has the developer diligently pursued the completion of the proposed development during the 18 months?
      (2)   Will the granting of the extension be detrimental to public safety, health or welfare or injurious to other property?
(Ord. passed 6-5-2012)