1105.16 SUBGRADE TESTING.
   Prior to the submittal of design data and construction drawings, the developer shall hire an independent testing agency to take soil borings along the proposed roadway limits. The location of where the borings shall be taken will be determined by the Road Commissioner. In addition the location of these borings must be shown on the preliminary plan prior to it being approved. A minimum of two (2) bore samples shall be taken for any subdivision or one (1) bore sample per one thousand (1,000) feet of proposed roadway center lines. Once the borings have been taken, a report shall be submitted to the Village Road Commissioner specifying the type of soil that was encountered and the suitability of the soil for development purposes. The location of the borings shall be noted on the construction drawings. The cost of such borings and testing shall be the responsibility of the developer.
(Ord. 56-2005. Passed 10-3-05.)