1460.06 COMPLIANCE WITH ORDER REQUIRED; FAILURE TO COMPLY.
   (a)   After any order of the Building Inspector or the Board of Building Appeals made pursuant to this chapter shall have become final, no person to whom any such order is directed shall fail, neglect or refuse to obey any such order.
   (b)   If, after any order of the Building Inspector or the Board of Building Appeals made pursuant to this chapter becomes final, the person to whom such order is directed shall fail, neglect or refuse to obey such order, the Building Inspector may cause such person to be prosecuted under this chapter or institute any appropriate action to abate such building as a public nuisance.
   (c)   Whenever the required repair or demolition is not commenced within sixty days after any final notice and order issued under this chapter becomes effective:
      (1)   The Building Inspector shall cause the building described in such notice and order to be vacated by posting at each entrance thereto a notice reading:
   "DANGEROUS BUILDING DO NOT OCCUPY
   It is a first degree misdemeanor to occupy this building or to remove or deface this notice: Building Inspector City of London"
      (2)   No person shall occupy any building which has been posted as specified in this subsection. No person shall remove or deface any such notice so posted until the repair, demolition or removal ordered by the Building Inspector has been completed.
      (3)   The Building Inspector may, in addition to any other remedy herein provided, cause the building to be repaired to the extent necessary to correct the conditions which render the building dangerous, unsafe or substandard as set forth in the notice and order; or, if the notice and order required demolition, to cause the building to be sold and demolished or demolished and the materials, rubble or debris thereof removed and the lot cleaned. Any such repair or demolition work shall be accomplished and the cost thereof paid and recovered in the manner hereinafter provided. Any surplus realized from the sale of any such building or from the demolition thereof, over and above the cost of demolition and of cleaning the lot, shall be paid over to the person or persons lawfully entitled thereto.
(Ord. 167-95. Passed 8-3-95.)