(a) Required. After the adoption of this Zoning Code, it shall be unlawful to use or occupy any new or changed lot and/or structure, or to change the use of any existing lot and/or structure, until the Zoning Administrator issues a certificate of occupancy that states that the proposed use of the structure and/or land conforms to the requirements of this Zoning Code. The issuance of an occupancy certificate in no way relieves the recipient from compliance with all requirements of this Zoning Code and other applicable regulations.
(b) Temporary Certificates of Occupancy. A temporary certificate of occupancy may be issued by the Zoning Administrator (for a period not exceeding six months) allowing alterations to be made to, or allowing partial occupancy of, a building pending its completion.
(Ord. 186-91. Passed 10-15-92.)