1478.11 REVOCATION OF CONDITIONAL USE PERMIT; ABANDONMENT.
   (a)   Revocation. Grounds for revocation of the conditional use permit, pursuant to the City of London Zoning Code, shall be limited to one of the following findings:
      (1)   The facility fails to comply with the relevant requirements of this chapter as they exist at the time of annual review and the permittee has failed to supply assurances acceptable to the Public Safety and Service Director that the facility will be brought into compliance within 120 days;
      (2)   The permittee has failed to comply with the conditions of approval imposed; or
      (3)   The facility has not been properly maintained.
   (b)   Abandonment. Any antenna or tower that is not operated for a continuous period of six months shall be considered abandoned. In such circumstances, the following shall apply:
      (1)   The owner of such antenna or tower shall remove said antenna and/or tower, including all supporting equipment and building(s), within ninety days of receipt of notice from the Public Safety and Service Director notifying the owner of such abandonment. If removal to the satisfaction of the Public Safety and Service Director does not occur within said ninety days, the City Attorney may order removal utilizing the established bond as provided under Section 1478.09 and salvage said antenna or tower and all supporting equipment and building(s). If there are two or more users of a single tower, then this provision shall not become effective until all operations of the tower cease.
      (2)   The recipient of a conditional use permit for a telecommunications facility under this chapter shall notify the Public Safety and Service Director when the facility is no longer in operation.
(Ord. 242-98. Passed 1-7-99.)