§ 1001.103 PUBLIC UTILITIES.
   Telephone, electric, cable, gas service lines and/or other public utilities are to be placed underground in accordance with city standards.
   (1)   Developers shall apply for city permits to install underground utilities in public rights-of-way.
   (2)   The city shall approve all utilities prior to installation.
   (3)   Public utilities shall be installed in a joint trench in accordance with city standards.
   (4)   Conduit shall be installed for all road crossings.
   (5)   Public utility installation shall not occur until one week after all curb has been backfilled.
(Ord. 04-03, passed 2-24-2003)