§ 98.14 NOTIFICATION.
   (A)   An applicant for an excavation permit or its contractor shall notify a notification center established pursuant to Tex. Utility Code Chapter 251, prior to conducting any work in the right-of-way such as excavating, drilling, underground boring, jacking, or open cutting.
   (B)   A permit holder shall provide the city with the following information not less than 48 hours before beginning work under the utility construction permit:
      (1)   The reference number received from the notification center;
      (2)   The exact dates and time work will be performed under the permit; and
      (3)   The name, address and telephone number of the person who will perform the work, including a representative who will be available at all times during construction, and who may be contacted by the phone 24 hours per day.
   (C)   The notice of work must be in writing and may be sent by facsimile transmission.
(Ord. 1018-2, passed 2-11-2019)