§ 153.243  IMPLEMENTATION OF CONDITION USE PERMIT.
   Unless the City Council issues a conditional use permit which either is specifically exempted from any time constraints or has some other specified time period for implementation, the applicant shall have a period of 24 months from date of issuance of the conditional use permit to secure a building permit for the project. If the applicant shall fail to obtain a building permit within the time allowed, the Administrator shall notify the applicant of a finding, and within 60 days of the notification, the Planning Board shall make a recommendation concerning the recession of the conditional use permit to the City Council. The City Council, after having conducted a public hearing to consider the recession, may then rescind the conditional use permit, or extend the life of the conditional use permit for a specified period of time. Due notice of the public hearing shall be given as prescribed in § 153.237 of this chapter.
(Prior UDO, § 13.10)  Penalty, see § 153.999