§ 54.037 EXISTING CONNECTIONS.
   (A)   Any user, other than a significant industrial user, required to obtain a wastewater discharge permit who was discharging wastewater into the POTW prior to the effective date of this code and who wishes to continue such discharges in the future, shall, within 60 days after said date, apply to the Town Manager for a wastewater discharge permit in accordance with § 54.039 of this chapter, and shall not cause or allow discharges to the POTW to continue after 120 days of the effective date of this code, except in accordance with a wastewater discharge permit issued by the Town Manager.
   (B)   Any significant industrial user required to obtain a wastewater discharge permit who was discharging wastewater into the POTW prior to the effective date of this code and who wishes to continue such discharges in the future, shall, within 60 days after said date, apply to the Town Manager for a wastewater discharge permit in accordance with § 54.039 of this chapter.
      (1)   In support of the application, the significant industrial user shall submit any and all information requested by the Town Manager as set forth on a form provided by the town.
      (2)   If additional pretreatment facilities or requirements are necessary to meet the pretreatment standards, the Town Manager, with assistance from available technical assistance that the Town Manager may seek, may establish a schedule and timetable for meeting pretreatment standards.
      (3)   The schedule shall contain increments of progress in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the significant industrial user to meet the applicable pretreatment standards.
      (4)   In no event shall the schedule exceed nine months or the significant industrial user be permitted to discharge into the POTW after the schedule deadline without the written consent of the Town Manager.
(Prior Code, § 155.4.3)