1830.02   PERMIT REQUIRED.
   No person shall install, deposit, park or leave any POD or similar devices on any property within the city without first obtaining a permit from the building department. A permit fee of $60.00 is required, with the option to purchase a 15-day extension for $20.00. The permit shall be for a time period not to exceed 30 days during which time the unit may be kept on the property. The 30 days will include loading and unloading time. No more than two permits may be issued for any lot or parcel of property in any 12-month period, unless a change in resident(s) occurs. Proof of lease or sale of the property must be presented to show the change in resident(s). If the person elects to move the POD to an off-site storage facility, the loading period shall not exceed 30 days. An additional permit will be required if the POD is not returned, unloaded within 30 days, within 12 months of the permit date.
(Ord. 224-22. Passed 10-10-22.)