1220.13   COMPLETION OF IMPROVEMENTS; RELEASE OF BOND.
   (A)   Upon satisfactory recommendation for approval of all improvements by the City Engineer or the County Engineer, the bond may be released, in writing, by the Planing Commission or the cashier's certified check may be returned to the developer. However, if the Commission finds that the improvements are not completed as specified, the checks or moneys may be used to complete such improvements.
   (B)   The construction of all improvements required by these Subdivision Regulations must be completed within one year from the date of the bond required in Section 1220.01. However, when unusual or exceptional factors exist, the Commission may grant an extension of time, upon the recommendation of the City Engineer or the County Engineer.
(Ord. 110-61. Passed 7-17-61.)