11-4-11: COMPLETION OF SUBDIVISION IMPROVEMENTS:
No subdivision final plat map or deed shall be recorded until all of the stipulations for approval have been met and all required improvements have been completed to the standards and specifications established by the City or other codes, laws, or regulations. In addition the following minimum requirements apply and may be added to by the Planning and Zoning Commission, or City Council:
   A.   Construction within the subdivision shall conform to all Federal and State regulations.
   B.   Construction drawings and construction within the subdivision shall conform to the Lewiston City standards and specifications. This document shall be available in the Office of the Zoning Administrator.
   C.   Permits must be obtained for construction of the infrastructure facilities within the subdivision.
   D.   There shall be a schedule of fees for all services required for the review of infrastructure in the Office of the Zoning Administrator. All fees within the schedule of fees shall be passed by a resolution of the City Council.
   E.   Any work which begins prior to the issuance of a permit may be assessed an administrative penalty equal to two hundred percent (200%) of the cost of any fees and permits plus one thousand dollars ($1,000.00).
   F.   A preconstruction conference with the Public Works Director may be required not less than forty eight (48) hours prior to the commencement of construction activities.
   G.   The contractor shall notify the Zoning Administrator not less than forty eight (48) hours prior to the commencement of construction.
   H.   Within thirty (30) days of the completion of improvements, the subdivider shall submit "as built" drawings of subdivision improvements prepared by or under the supervision of a professional licensed to prepare such work in the State of Utah. Failure to submit such drawings shall result in a hold being placed on issuance of any building permits. (Ord. 13-01, 4-16-2013)