§ I-6.010 WATER FACILITIES.
   General.
   (A)   In all zoning districts, subdivisions containing 15 feet or more lots shall install a public water system and provide the following information:
      (1)   Written authorization from a local water supplier or a water right obtained is required to show that adequate water is available to serve the proposed subdivision;
      (2)   All water supply improvements must be shown on the construction plans. All water supply systems shall be designed by a state registered professional engineer;
      (3)   Design calculation reports shall be submitted with construction plans;
      (4)   Under layout plan, preliminary plat, and final plat: a master plan is required for un-platted balances to prevent piecemeal water system development; and
      (5)   A water system serving 14 or fewer lots may also be subject to state and/or federal regulations.
   (B)   All public water systems are required to obtain DANR department approval per ARSD 74:53:04 and ARSD 74:53:05. Plans and specifications for these systems are required to be prepared by licensed engineers and are required to receive Department approval prior to construction.
(Ord. 14-04, passed 6-30-2015, Ch. 7, Art. 10; Ord. 24-01, passed 5-14-2024)