9-3-21: FINAL ACCEPTANCE:
   A.   LaVerkin City's representative will give written notice to the contractor that the work is acceptable on the basis that:
      1.   The contractor has requested that work be given final acceptance; and
      2.   The LaVerkin City representative is satisfied that the work has been completed and the contractor's other obligations under the submitted documents have been fulfilled,
   B.   Otherwise, LaVerkin City's representative will indicate in writing to the contractor the reasons for refusing to recommend final acceptance. The contractor shall then make the necessary corrections as outlined above and resubmit request for final acceptance approval. (Ord. 2006-22, 7-5-2006; amd. Ord. 2007-24, 8-15-2007)