9-3-20: FINAL INSPECTION:
When the contractor certifies that the work is fully completed, a final inspection shall be made. The LaVerkin City representative will prepare a final inspection punch list and will deliver such list to the contractor in writing. The list shall be considered complete and final, and no additional punch list items will be presented to the contractor, except for latent defects, damage due to punch list rework, fraud, gross mistakes amounting to fraud, or work required by the contract documents. Delivery of the final inspection punch list or accomplishment of the work thereon by the contractor does not relinquish any of LaVerkin City's rights under the correction or removal process or the warranty and guarantee provisions of these specifications. (Ord. 2006-22, 7-5-2006; amd. Ord. 2007-24, 8-15-2007)