7-3-9: ROAD CLOSURES:
   A.   Arrangements for partial or complete street closure permits shall be obtained through the LaVerkin City representative. An advance notice of forty eight (48) hours for major streets and twenty four (24) hours for local streets and alleys is required from the contractor.
   B.   Unless otherwise approved by the LaVerkin City representative, all existing traffic lanes shall be maintained open to traffic.
   C.   Local access shall be maintained to all properties on the project at all possible times. When local access cannot be maintained, the contractor must notify the affected property owner at least twenty four (24) hours in advance. Access shall be restored the same day of completion of work which caused loss of access.
   D.   A traffic lane shall not be considered as satisfactorily open to traffic unless it is paved with hot mix or cold mix asphalt paving if surrounded by or adjacent to existing pavement. Where pavement did not previously exist or where all of the existing pavement has been removed, a traffic lane shall not be considered as satisfactorily open to traffic unless it is graded reasonably smooth and maintained dust free as directed by the LaVerkin City representative.
   E.   At any time project construction shall require the closure or disruption of traffic in any roadway or alley such that normal refuse collection will be interfered with, the contractor shall, prior to causing such closure or disruption, make arrangements with the appropriate refuse removal service in order that collection service can be maintained. (Ord. 2006-23, 7-5-2006)