§ 154.24  FINAL PLAN APPROVAL.
   (A)   The petitioner shall submit to the zoning official sufficient copies of the final PUD site plan for all or any part of the development, in accordance with the uses and concepts as shown on the approved PUD site plan.  The final PUD plan for each stage shall include all the information required by this chapter and shall also comply with any additional requirements of the Plan Commission when it granted preliminary approval.
   (B)   Copies of the final PUD site plan as submitted shall be distributed promptly by the Zoning official to the appropriate county agencies for review and comment regarding the legal requirements of the county.
   (C)   The Commission shall approve or disapprove the proposed final PUD plan and issue a written decision on the reasons for the decision within 30 days of the conclusion of the public hearing.  The petitioner shall be supplied a copy of the written decision.
   (D)   Approval of the final PUD site plan shall entitle the owner to apply for building permit(s).
(`88 Code, § 8-147)  (Ord. 98-20, passed 11-10-98)