The subdivider shall provide the subdivision with a complete water main supply system which shall be connected to an existing approved municipal or community water supply, except that when a municipal or community water supply is not available, the subdivider shall provide one of the following:
(A) A complete community water supply system to be provided in accordance with the minimum requirements of the state Board of Health.
(1) The plans for the installation of a water main supply system shall be provided by the subdivider and approved by the state Board of Health.
(2) Upon completion of the water supply installation, the plans for the system as built shall be filed with the Commission.
(B) An individual water supply on each lot in the subdivision in accordance with the minimum requirements of the state Board of Health.
(`88 Code, § 8-111) (Ord. 98-20, passed 11-10-98)