Construction of all towers must begin within 100 days after issuance of a building permit. Once construction begins, all towers must be completed within 90 days. Any permit issued prior to the adoptive date of this amended chapter must have construction started within 180 days from the date of adoption. If construction does not begin within 180 days of issuance, then the permit shall be void. All tower placements must be pursuant to the amended provisions of this chapter thereafter. Extensions may be granted at the discretion of the Building Commissioner.
(`88 Code, § 8-22) (Ord. 98-20, passed 11-10-98; Am. Ord. 2000-14, passed 6-13-00; Am. Ord. 2007-25, passed 12-4-07)