§ 52.12  REQUIREMENTS FOR STORMWATER MANAGEMENT PLAN APPROVAL.
   (A)   Stormwater Management Plan required for all developments.
      (1)   No application for development will be approved unless it includes a Stormwater Management Plan detailing how runoff and associated water quality impacts resulting from the development will be controlled or managed. This plan must be prepared by an individual approved by the county and must indicate whether stormwater will be managed on-site or off-site and, if on-site, the general location and type of practices.
      (2)   The Stormwater Management Plan(s) shall be referred for comment to all other interested agencies, and any comments must be addressed in the final approved Stormwater Management Plan. This final plan must be signed by a licensed Professional Engineer (PE), who will verify that the design of all stormwater management practices meet the submittal requirements outlined in the Submittal Checklist provided by the MS4 Coordinator. No land-disturbing activities shall commence until a satisfactory final Stormwater Management Plan, or a waiver thereof, shall have undergone a review and been approved by the MS4 Coordinator after determining that the plan or waiver is consistent with the requirements of this subchapter.
   (B)   Stormwater Management Plan Requirements.
      (1)   A  Stormwater Management Plan shall be required will all permit applications and will include sufficient information (such as maps, hydrologic calculations and the like) to evaluate the stormwater effects of the project, the potential impacts of all proposed development of the site, both present and future, on the water resources, and the effectiveness and acceptability of the measures proposed for managing stormwater generated at the project.
      (2)   The intent of this planning process is to determine the type of stormwater management measures necessary for the proposed project; and ensure adequate planning for management of stormwater runoff from future development. To accomplish this goal, the following information shall be included in the Stormwater Management Plan:
         (a)   A map (or maps) indicating the location of existing and proposed buildings, roads, parking areas, utilities, structural stormwater management and sediment control facilities. The map(s) will also clearly show proposed land use with tabulation of the percentage of surface area to be adapted to various uses; drainage patterns; locations of utilities, roads and easements; the limits of clearing and grading. A written description of the site plan and justification of proposed changes in natural conditions may also be required.
         (b)   Sufficient engineering analysis to show that the proposed stormwater management measures are capable of controlling runoff from the site in compliance with this subchapter and the specifications of the Reference Manuals.
         (c)   A written or graphic inventory of the natural resources at the site and surrounding areaas it exists prior to the commencement of the project and a description of the watershed and its relation to the project site. This description should include a discussion of soil conditions, forest cover, topography, wetlands, and other native vegetative areas on the site. Particular attention should be paid to environmentally sensitive features that provide particular opportunities or constraints for development.
         (d)   A written description of the required maintenance burden for any proposed stormwater management facility.
         (e)   The MS4 Coordinator may also require a Stormwater Management Plan to consider the maximum development potential of a site under existing zoning, regardless of whether the applicant presently intends to develop the site to its maximum potential.
         (f)   For development or redevelopment occurring on a previously developed site, an applicant shall be required to include within the Stormwater Management Plan measures for controlling existing stormwater runoff discharges from the site in accordance with the standards of this subchapter to the maximum extent practicable.
         (g)   Contact information. The name, address, and telephone number of all persons having a legal interest in the property and the tax reference number and parcel number of the property or properties affected.
         (h)   Topographic base map. A “one inch equals 200 feet” topographic base map of the site which extends a minimum of 100 feet beyond the limits of the proposed development and indicates existing surface water drainage including streams, ponds, culverts, ditches, and wetlands; current land use including all existing structures; locations of utilities, roads, and easements; and significant natural and manmade features not otherwise shown.
         (i)   Calculations. Hydrologic and hydraulic design calculations for the predevelopment and post-development conditions for the design stormsspecified in this subchapter. Such calculations shall include:
            1.   Description of the design storm frequency, intensity and duration;
            2.   Time of concentration;
            3.   Soil curve numbers or runoff coefficients;
            4.   Peak runoff rates and total runoff volumes for each watershed area;
            5.    Infiltration rates, where applicable;
            6.   Culvert capacities;
            7.   Flow velocities;
            8.   Data on the increase in rate and volume of runoff for the design storms referenced in the Reference Manuals or other ordinances; and
            9.   Documentation of sources for all computation methods and field test results.
         (j)   Soils information.  If a stormwater management control measure depends on the hydrologic properties of soils (such as infiltration basins), then a soils report shall be submitted. The soils report shall be based on on-site boring logs or soil pit profiles. The number and location of required soil borings or soil test pits shall be determined based on what is needed to determine the suitability and distribution of soil types present at the location of the control measure.
         (k)   Maintenance and Repair Plan.  The design and planning of all stormwater management facilities shall include detailed maintenance and repair procedures to ensure their continued function. These plans will identify the parts or components of a stormwater management facility that need to be maintained and the equipment and skills or training necessary. Provisions for the periodic review and evaluation of the effectiveness of the maintenance program and the need for revisions or additional maintenance procedures shall be included in the plan.
         (l)   Landscaping Plan. The applicant must present a detailed plan for management of vegetation at the site after construction is finished, including who will be responsible for the maintenance of vegetation at the site and what practices will be employed to ensure that adequate vegetative cover is preserved. This plan must be prepared by a registered Engineer, Landscape Architect, or by the Soil Conservation District.
         (m)   Maintenance easements. The applicant must ensure access to all stormwater treatment practices at the site for the purpose of inspection and repair by securing all the maintenance easements needed on a permanent basis. These easements will be recorded with the plan and will remain in effect even with the transfer of title to subsequent property owners.
         (n)   Maintenance agreement. The applicant must execute an easement and an inspection and maintenance agreement binding on all subsequent owners of land served by an on-site stormwater management measure in accordance with the specifications of this subchapter.
         (o)   Erosion and sediment control plans for construction of stormwater management measures.  The applicant must prepare an erosion and sediment control plan for all construction activities related to implementing any on-site stormwater management practices.
         (p)   Other permits. The applicant shall assure that all other applicable permits have been acquired for the site prior to approval of the final stormwater management plan.
      (3)   Stormwater Management Concept Plan. If deemed necessary by the MS4 Coordinator, a Stormwater Management Concept Plan can be required to be submitted by the developer, prior to the preparation of a Stormwater Management Plan, to document for the MS4 Coordinator the overall impact and the intent of the type(s) of stormwater management measures necessary for the proposed project, on a conceptual basis.
      (4)   Performance bond/security.
         (a)   The county requires the submittal of a performance security or bond prior to issuance of a permit in order to insure that the stormwater practices are installed by the permit holder as required by the approved stormwater management plan. The amount of the installation performance security shall be the total estimated construction cost of the stormwater management practices approved under the permit, plus 25%. The performance security shall contain forfeiture provisions for failure to complete work specified in the stormwater management plan.
         (b)   The installation performance security shall be released in full only upon submission of "as-built plans" and written certification by a registered professional engineer that the stormwater practice has been installed in accordance with the approved plan and other applicable provisions of this subchapter. The MS4 Coordinator will make a final inspection of the stormwater practice to ensure that it is in compliance with the approved plan and the provisions of this subchapter. Provisions for a partial pro-rata release of the performance security based on the completion of various development stages can be done pursuant to a partial release determination made by the MS4 Coordinator.
(Ord. 2007-05, passed 4-17-07)