Application for approval of final plat shall be submitted in writing to the City Engineer, together with the tracing and ten (10) prints of the final plat, one (1) reduced copy no larger than 11” x 17”, and such other maps or data as required. The applicant shall submit all fees as applicable for a final plat, as established by City Council. The application shall be submitted within two (2) years after approval of the preliminary plat; otherwise, approval of the preliminary plat shall become null and void unless an extension is granted by the Planning Commission. Within ten (10) working days, the City Engineer shall review the application, and determine if such application is complete and if all applicable requirements of the Subdivision Regulations have been met. If he/she determines that all applicable requirements have been met, the City Engineer shall transmit the application to the Planning Commission at its next regularly scheduled meeting, which shall be deemed the date of submission of the final plat.