(A) The property to which the utility main extends must be platted and the developer must follow all development guidelines and building codes as well as construction standards and specifications of the town.
(B) All easements, dedications, and public rights-of-way necessary to construct the main extension must be acquired by the developer at the developer's expense and filed in the county deed records by the town.
(C) No reimbursement shall be allowed for on-site utility lines unless said lines are required to be oversized.
(D) No reimbursement shall be allowed for off-site main extensions of less than 200 feet. If the site extension from an existing utility main to the developer’s property line is greater than 200 feet, this section may be utilized.
(E) No reimbursement shall be allowed for any utility main extension that is shown on the water or wastewater capital improvements plan.
(Ord. 353, passed 7-10-2013)