From and after March 21, 2013, the policy set out in this section applies to the connection of service to the town’s sanitary sewer system:
(A) If town sanitary sewer system service is available within 100 feet of the subject property, the use of an existing septic tank may be continued until the privately owned sanitary septic system ceases to be a functioning septic tank. No privately owned sanitary septic system can be installed after the date of sewer availability.
(B) The charge to the property owner by the town for connecting to available town sewer shall be a tap fee, plus the applicable capital recovery fee as set forth in the town fee schedule.
(C) A 50% discount on the tap fee will be allowed for any connection made to the town sanitary sewer system if the tap fee, plus the capital recovery fee is paid within 30 days from the date of sewer availability.
(Ord. 345, passed 3-21-2013)