§ 151.091 PROCEDURE.
   As-built drawings shall be initially submitted in the form of two sets of prints with blue or black lines. Upon the approval of the as-built drawings by the Village Engineer, complete sets, of reproducible mylar drawings, a minimum of three mils thick, together with two complete sets of blue-line or black-line prints, shall be submitted to the Village Engineer for distribution and archives. The village may, at their discretion, also require the plans to be submitted in digital format. The number of as-built mylar plan sets shall be determined by the village. The applicant shall receive copies of any inspection/observation reports from the Village Engineer. This information is only intended to supplement their own, as-built survey, contractor reports, and own field observation and are not intended to be a complete record for all construction activities for the subject project or the only source of documentation to provide the as-built information required herein.
(Ord. 31.26, passed 5-13-13)