§ 52.24 AS-BUILT PLANS.
   Prior to the acceptance of any sewer system and prior to the removal of the bulkhead as required in § 52.17 (except under extenuating circumstances as may be approved by the Director), as-built plans shall be provided to the Oakland County Department of Public Works. The as-built plans shall show a statement by a registered engineer or surveyor certifying this to be “as-built plans” and shall include, but not be limited to, length of sewer, invert elevation, locations with respect to property lines, wye and riser locations and depths, and sewer material and joints used.
(Ord. 23.27, passed 1-8-90)