(a) Calculated runoff rate. Erosion and sedimentation control measures, structures, and devices shall be so planned, designed, and constructed as to provide protection from the calculated maximum peak rate of runoff from the ten-year storm or 25-year storm when projects will discharge into a lake or natural watercourse. Runoff rates shall be calculated using the procedures in the USDA, Soil Conservation Service's "National Engineering Field Manual for Conservation Practices," or other acceptable calculation procedures.
(b) HQW zones. In High Quality Water (HQW) zones, the following standards shall apply:
(1) Limit on uncovered area. Uncovered areas in HQW zones shall be limited at any time to a maximum total area of 20 acres within the boundaries of the tract. Only the portion of the land disturbing activity within an HQW zone shall be governed by this section. Larger areas may be uncovered within the boundaries of the tract with the written approval of the director.
(2) Maximum peak rate of runoff protection. Erosion and sedimentation control measures, structures, and devices within HQW zones shall be planned, designed and constructed to provide protection from the runoff of the 25-year storm which produces the maximum peak rate of runoff as calculated according to procedures in the USDA, Soil Conservation Service's "National Engineering Field Manual for Conservation Practices" or according to procedures adopted by any other agency of the state or the United States or any generally recognized organization or association.
(3) Settling efficiency. Sediment basins within HQW zones shall be designed and constructed such that the basin will have a settling efficiency of at least 70 percent for the 40 micron (0.04 millimeter) size particle transported into the basin by the runoff of that two-year storm which produces the maximum peak runoff as calculated according to procedures in the USDA Soil Conservation Service's "National Engineering Field Manual for Conservation Practices" or according to procedures adopted by any other agency of the state or the United States or any generally recognized organization or association.
(4) Grade. Newly constructed open channels in HQW zones shall be designed and constructed with side slopes no steeper than two horizontal to one vertical if a vegetative cover is used for stabilization unless soil conditions permit a steeper slope or where the slopes are stabilized by using mechanical devices, structural devices or other acceptable ditch liners. In any event, the angle for side slopes shall be sufficient to restrain accelerated erosion.
(5) Ground cover. Ground cover sufficient to restrain erosion must be provided for any portion of a land disturbing activity in a HQW zone within 15 working days or 60 calendar days following completion of construction or development, whichever period is shorter.
(Code 1989, § 96.08; Ord. of 6-12-2007)