Sec. 14-47. Duties and responsibilities of the floodplain administrator.
   The floodplain administrator shall assume and perform all such duties and responsibilities as are necessary to administer these regulations including, without limitation, those listed herein.
      (1)   Review all floodplain development applications and issue permits for all proposed development within special flood hazard areas to ensure that the requirements of this article have been satisfied.
      (2)   Review all proposed development within special flood hazard areas to ensure that all necessary local, state, and federal permits have been received.
      (3)   Notify adjacent communities and the North Carolina Department of Crime Control and Public Safety, Division of Emergency Management, State Coordinator for the National Flood Insurance Program, prior to any alteration or relocation of a watercourse, and submit evidence of such notification to the Federal Emergency Management Agency.
      (4)   Ensure that maintenance is provided within the altered or relocated portion of said watercourse so that the flood-carrying capacity is maintained.
      (5)   Prevent encroachments into floodways and non-encroachment areas unless the certification and flood hazard reduction provisions of section 14-76 are met.
      (6)   Obtain actual elevation (in relation to mean sea level) of the reference level (including basement) and all attendant utilities of all new and substantially improved structures, in accordance with the provisions of section 14-46.
      (7)   Obtain actual elevation (in relation to mean sea level) to which all new and substantially improved structures and utilities have been floodproofed, in accordance with the provisions of section 14-46.
      (8)   Obtain actual elevation (in relation to mean sea level) of all public utilities in accordance with the provisions of section 14-46.
      (9)   When floodproofing is utilized for a particular structure, obtain certifications from a registered professional engineer or architect in accordance with the provisions of sections 14-46 and 14-73(2).
      (10)   Make the necessary interpretation where interpretation is needed as to the exact location of boundaries of the special flood hazard areas, floodways, or non-encroachment areas (for example, where there appears to be a conflict between a mapped boundary and actual field conditions). The person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation as provided in this section.
      (11)   When base flood elevation (BFE) data have not been provided in accordance with the provisions of section 14-7, obtain, review, and reasonably utilize any base flood elevation (BFE) data, along with floodway data or non- encroachment area data available from a federal, state, or other source, including data developed pursuant to section 14-74(2)b, in order to administer the provisions of this article.
      (12)   When base flood elevation (BFE) data are provided but no floodway or non-encroachment area data have been provided in accordance with the provisions of section 14-7, obtain, review, and reasonably utilize any floodway data or non-encroachment area data available from a federal, state, or other source in order to administer the provisions of this article.
      (13)   When the lowest floor and the lowest adjacent grade of a structure or the lowest ground elevation of a parcel in a special flood hazard area is above the base flood elevation, advise the property owner of the option to apply for a letter of map amendment (LOMA) from FEMA. Maintain a copy of the letter of map amendment (LOMA) issued by FEMA in the floodplain development permit file.
      (14)   Permanently maintain all records that pertain to the administration of this article and make these records available for public inspection, recognizing that such information may be subject to the Privacy Act of 1974, as amended.
      (15)   Make on-site inspections of work in progress. As the work pursuant to a floodplain development permit progresses, the floodplain administrator shall make as many inspections of the work as may be necessary to ensure that the work is being done according to the provisions of the local ordinance and the terms of the permit. In exercising this power, the floodplain administrator has a right, upon presentation of proper credentials, to enter on any premises within the jurisdiction of the community at any reasonable hour for the purposes of inspection or other enforcement action.
      (16)   Issue stop-work orders as required. Whenever a building or part thereof is being constructed, reconstructed, altered, or repaired in violation of this article, the floodplain administrator may order the work to be immediately stopped. The stop-work order shall be in writing and directed to the person doing or in charge of the work. The stop-work order shall state the specific work to be stopped, the specific reason for the stoppage, and the condition under which the work may be resumed. Violation of a stop-work order subjects the perpetrator to a civil penalty pursuant to section 14-13.
      (17)   Revoke floodplain development permits as required. The floodplain administrator may revoke and require the return of the floodplain development permit by notifying the permit holder in writing stating the reason for the revocation. Permits shall be revoked for the following reasons:
         a.   Any substantial departure from the approved application, plans, and specifications;
         b.   Refusal or failure to comply with the requirements of state or local laws; or
         c.   False statements or misrepresentations made in securing the permit. Any floodplain development permit mistakenly issued in violation of an applicable state or local law may also be revoked.
      (18)   Make periodic inspections throughout the special flood hazard areas within the jurisdiction of the community. The floodplain administrator and each member of his inspections department shall have a right, upon presentation of proper credentials, to enter on any premises within the territorial jurisdiction of the department at any reasonable hour for the purposes of inspection or other enforcement action.
      (19)   Follow through with the corrective procedures of section 14-48.
      (20)   Review, provide input, and make recommendations for variance requests.
      (21)   Maintain a current map repository to include, without limitation, the FIS Report, FIRM and other official flood maps and studies adopted in accordance with the provisions of section 14-7, including any revisions thereto, including letters of map change, issued by FEMA. Notify the state and FEMA of mapping needs.
      (22)   Coordinate revisions to FIS reports and FIRMs, including letters of map revision based on fill (LOMR-Fs) and letters of map revision (LOMRs).
(Code 1989, § 95.032)