§ 154.106 PROCESSING OF PUDS.
   Planned unit developments must be processed as a conditional use, except that an expansion to an existing commercial PUD involving six or fewer new dwelling units or sites since the date this chapter was adopted is permissible as a permitted use provided the total project density does not exceed the allowable densities calculated in the project density evaluation procedures in § 154.109. Approval cannot occur until the environmental review process (EAW/EIS) is complete.
(Ord. 195, passed 2-3-1992)