After the issuance of any permit hereunder, the owner or contractor shall cause to be made such inspections of work being done under such permit as are necessary to ensure full compliance with this code and the terms of the permit.
(A) There shall not be less than eight inspections for every permit, unless excused in writing for cause by the Director or his or her designated representative, which inspections shall be made in the following scheduled order:
(1) Footing pre-pour inspection;
(2) Footing inspection;
(3) Foundation inspection. Foundation as-built survey. Prior to requesting a foundation inspection for a new one through four family residential home, the general contractor shall submit a foundation as-built survey (survey) stamped by an Indiana licensed land surveyor. The survey must comply with the approved site plan for the building permit, prior to scheduling the foundation inspection;
(4) Rough H.V.A.C. inspection;
(5) Rough plumbing inspection;
(6) Rough electric inspection;
(7) Rough framing inspection;
(8) Electric service inspection;
(9) Final H.V.A.C. inspection;
(10) Final plumbing inspection;
(11) Final electric inspection;
(12) Final framing inspection.
(B) Work not in compliance with code or not ready for inspection. There shall be an additional fee of $50 if an inspection is made and the work is not in compliance with the intent of this code.
(C) Reinspection. Upon payment of $50, a re-inspection shall be required before any further construction, other than the correction of the defect, is carried out.
(Prior Code, § 151.019) (Ord. passed 11-2-1970; Ord. 1458A, passed 4-11-2000; Ord. 2165, passed 9-12-2006; Ord. 2490, passed - -2017)