(A) Suspension. When, during the construction of an onsite wastewater treatment system, a licensed installation contractor violates the provisions of this chapter or is not constructing the system in accordance with the approved site plan, the Health Officer shall suspend the construction approval issued pursuant to the site plan approval.
(B) Suspension notice. The notice of suspension shall be in writing, posted at the site and mailed to the owner and licensed installation contractor, as applicable, by regular, certified or registered mail. The notice shall contain information as follows:
(1) A statement that any further work on the onsite wastewater treatment system is prohibited.
(2) An explanation of the reason for the suspension of construction approval.
(3) An outline of actions and the process required to avoid the revocation of the plan approval, if determined.
(4) A statement that a written corrective action plan must be submitted within ten business days or the approval is subject to revocation.
(C) Revocation of plan approval. If the Health Officer does not receive written actions or drawn plans to correct the problems that caused the suspension of the construction approval within ten business days of the date of the notice, the Health Officer may issue notice revoking the plan approval in accordance with § 171.238.
(Ord. [Bd of Health Ord., Art. V], passed 11-12-1996; Ord. [Bd of Health Ord., Art. V], passed 11-12-2013; Ord. 24-1005, passed 8-13-2024)