(A) The use must not cause significant adverse impact to surface or ground water resources.
(B) Dewatering to obtain materials intersecting the groundwater shall not be allowed. The use of equipment such as draglines, trackhoes and backhoes to obtain materials intersecting groundwater shall not be allowed.
(C) Increased stormwater run-off must be retained on-site with retention or detention ponds.
(D) All activities on the subject property with the potential to impact water quality will be conducted in a manner consistent with required permits issued by state and federal agencies. The Planning Commission may require other standards it deems reasonably necessary.
(Ord. 508, passed 9-12-16)