(A) Upon receiving notice of a primary plat application, the Plan Director shall advise the City Engineer of the project. The petitioner shall then transfer two copies of the plans to the City Engineer for the purpose of reviewing the drainage plan for the project. If a legal drain is located upon or adjacent to the subdivision property, the petitioner shall also transfer two copies of the plans to the Howard County Drainage Board for review.
(B) The City Engineer shall review the drainage plan for said project and shall identify any problems or deficiencies in the plan. The City Engineer shall notify the Plan Director and petitioner of any such problems, thereby allowing appropriate time for adjustments and modifications to be made to the drainage plan for the project.
(C) After final review of the drainage plan and upon approval by the City Engineer and Howard County Drainage Board if appropriate, the plan can be presented to the Plan Commission.
(Ord. 6405, passed 4-10-06)