§ 97.17 RIGHT-OF-WAY EXCAVATION PERMIT FEES.
   (A)   A separate permit application shall be required for each individual right-of-way cut.
      (1)   Unless otherwise stated, permits being requested pursuant to § 97.16 shall require a minimum $50 application fee to be paid upon the receipt of the approved permit.
      (2)   Permits being requested pursuant to § 97.16(C)(10) require a minimum $25 application fee to be paid upon the receipt of the approved permit.
      (3)   In addition to the fee assessed under division (A)(1) above, a permit sought under § 97.16(C)(8) shall require an additional fee of $.10 per foot if the trench is extended in excess of 100 feet.
   (B)   A separate permit fee shall be assessed, at the time of permit approval, under the following conditions:
      (1)   Excavation of pavement, curb, or sidewalk resurfaced within 12 months of the right-of-way excavation application shall require an additional fee of $300.
      (2)   Excavation of pavement, curb, or sidewalk resurfaced within 24 months of the right-of-way excavation application shall require an additional fee of $200.
      (3)   Excavation of pavement, curb, or sidewalk resurfaced within 36 months of the right-of-way excavation application shall require an additional fee of $100.
      (4)   Excavation of pavement, curb, or sidewalk resurfaced greater than 36 months before the right-of-way application shall require an additional fee of $50.
      (5)   For any surface covered under § 97.16(D), an additional fee of $100 shall be required upon receipt of an approved right-of-way excavation.
(Ord. 6567, passed 12-8-08; Am. Ord. 6850, passed 12-12-16) Penalty, see § 97.99