§ 155.85 MISCELLANEOUS UTILITY STANDARDS.
   (A)   Prior to installation of any utilities, the Developer shall arrange and facilitate a "utility coordination" meeting. A representative from each potential utility provider (sanitary sewer, storm sewer, water, gas, cable, electric, telephone and the like) must be invited. If the total attendance is not satisfactory to the City Engineer, the meeting shall be rescheduled or continued. The purpose of this meeting is to coordinate all utility work and avoid conflicts and inefficiencies, in addition to promoting an effective, predictable and appropriate system of buried utilities.
   (B)   All utility lines, including electrical power, gas, telephone, cable, sewer, and water shall be located underground throughout the subdivision. The location of utility lines shall be shown on the construction plans. Location of the utilities shall be shown in a cross section, for every significantly different cross section. Service connections to the property lines of each lot in the development shall be provided by the utility or subdivider.
   (C)   Utility installations within off-site easements must be coordinated with property owners prior to the commencement of work.
(Ord. 6405, passed 4-21-06)