§ 155.455 INFORMATION TO BE SUBMITTED.
   (A)   The following information, in addition to information as required and as may be applicable for site plan review under §§ 155.330 through 155.335 must be submitted as part of the site plan review for wind energy system(s) of rated capacities of more than ten kW and/or for systems over 75 feet in total height. The following, as applicable, shall also be submitted for MET towers:
      (1)   Survey of the property showing property boundaries and existing features such as land contours, large trees, buildings, structures, roads (rights-of-way), utility easements, land use, zoning district, ownership of property and vehicular access;
      (2)   Plan(s) showing the proposed location and number of turbine towers, underground and overhead wiring (including depth of underground wiring), access roads (including width) substations and accessory structures;
      (3)   Photo exhibits visualizing the proposed wind energy system;
      (4)   Stamped and signed drawings from a state licensed structural engineer providing the details of the foundation and anchoring system as recommended by the manufacturer. A description of the wind energy system(s) height and design, including cross section, elevation and diagram of the foundation and anchoring system; the Planning Commission and/or the Zoning Administrator or Building Official may require a soil analysis to determine the suitability of the proposed location;
      (5)   Supporting documentation shall be submitted, where required, indicating that the applicant has received approval to install a wind energy system(s) under state, federal and local laws and regulations, including Federal Aviation Administration (FAA), the Michigan Tall Structures Act (Pub. Act 259 of 1959, being M.C.L.A. §§ 259.481 et seq.), the Michigan Airport Zoning Act (Pub. Act 23 of 1950, being M.C.L.A. §§ 259.431 et seq.), and state and local building codes. The FAA will issue a signed statement when the precise location(s) has been determined. Building permits will not be issued prior to receiving all signed statements, but a special use permit may be granted. Where a wind energy system does not require state or federal approval, construction permits may be issued; and
      (6)   A certificate of insurance with a minimum of $1,000,000 liability coverage per incidence, per occurrence shall be required. An expired insurance certificate or an unacceptable liability coverage amount is grounds for revocation of the use permit.
   (B)   Information required as part of an administrative site plan review for a wind energy system with a rated capacity of ten kW or less, and 75 feet or less in total height.
      (1)   A site plan at an appropriate scale showing the proposed location of the wind energy system, and any structures;
      (2)   Standard drawings of the wind turbine structure including the tower, base, footings, cross-section and connection and certification of the tower and turbine showing compliance with applicable building codes and recognized standards;
      (3)   Plan(s) showing the proposed location of turbine tower(s), underground wiring (including depth of underground wiring), access road, if any, and accessory structures;
      (4)   Documentation from the manufacturer, including full specifications and manufacturer recommended installation procedures;
      (5)   Proof of applicants public liability insurance; and
      (6)   Any other documentation to the satisfaction of the Zoning Administrator to ensure the health, safety and welfare of the residents of the township.
(Ord. 11-001, passed 1-18-2011)