An adequate storm drainage system shall be provided for each subdivision. Storm facilities shall be designed and constructed in accordance with standards established by the Village Engineer to prevent flooding and to properly dispose of storm waters.
Storm drainage facilities shall in each case be of sufficient capacity to accommodate potential runoff from the entire upstream drainage area, whether inside or outside the subdivision.
No subdivision shall be approved which would overload the existing downstream drainage facilities until provisions for downstream improvements or on-site detention satisfactory to the Village Engineer have been made.
Measures shall be taken to minimize erosion and its impacts during construction. Detailed erosion control plans setting forth the techniques to be used and a schedule for implementation shall be submitted with the final plat. Techniques, devices, or measures used shall be as approved by the Village Engineer.
(Ord. 3-89-06. Passed 3-1-89.)