§ 153.283 PROCEDURE.
   (A)   The applicant shall apply for a special use permit as outlined in § 153.362.
   (B)   Construction of an overhead transmission system requires approval of a single application of a transmission system (TS) special use permit application, which shall be reviewed by the Board of Commissioners through a quasi-judicial process.
   (C)   Construction of an overhead transmission system also shall require the approval of an application for a TS special use permit. The application for the TS conditional use permit shall specify the nature of the proposed overhead transmission system and shall propose:
      (1)   Conditions to ensure compatibility between the overhead transmission system and the surrounding area, and
      (2)   Satisfy the requirements of § 153.287.
(Ord. 06-20, passed 8-14-06; Am. Ord. 18-4, passed 6-14-21)