(A) Lot dimensions. All parcels shall have a minimum width of 75 feet.
(B) Lot area.
(1) The minimum building site shall be 15,000 square feet.
(2) The minimum building site for a duplex shall be 20,000 square feet.
(C) Reserved.
(D) Lot coverage.
(1) Maximum allowable lot coverage by principal use, all accessory structures, vehicular area and parking - 50%.
(2) Formula for lot coverage calculation when wetland soils are a portion of any lot. Soils classified as wetlands shall be factored into lot coverage calculations based on the following schedule:
(a) If the lot is composed of less than 25% of its total area in wetland soils, then 75% of that area classified as wetlands may be used in calculating lot coverage;
(b) If the lot has between 25% to 50% of its total area in soils classified as wetlands, then 50% of that area classified as wetlands may be used in calculating lot coverage;
(c) If the lot has between 50% and 75% of its total area in soils classified as wetlands, then 25% of that area classified as wetlands may be used in calculating lot coverage;
(d) If the lot has 75% or more of its total area classified as wetlands, none of that area classified as wetlands can be used in calculating lot coverage.
(3) Lot coverage within an estuarine area of environmental concern (AEC), as defined by the Coastal Area Management Act (CAMA), shall be limited to 20% and a minimum setback from the estuarine waters shall be 50 feet. (Exceptions: boardwalks, gazebos and other pedestrian access structures shall be permitted within the 50-foot setback but must be in accordance with CAMA regulations.)
(E) Drainage and stormwater runoff. All sites are required to follow the provisions of § 153.070.
(F) Land disturbance. See § 153.071.
(Am. Ord. 01-02, passed 2-28-01; Am. Ord. 01-13, passed 11-14-01; Am. Ord. 04-10, passed 5-26-04; Am. Ord. 18-4, passed 6-14-21)