907.09 FINISHED GRADING ON FILL OPERATIONS; REESTABLISHMENT OF SITE ON EXCAVATION AND REMOVAL OPERATIONS.
   Upon completion of the work allowed herein, compliance with the applicable provisions of the following sections is required:
   (a)   All pits, quarries, holes or other excavated areas shall be refilled with, and no new filling operation shall be conducted with, any material except clean, nonburnable fill containing no trash, refuse or harmful matter, and such excavated area and new filling operations shall be graded to the level of adjoining properties, or to an elevation from which all surface and other waters collected therein may find natural drainage therefrom. Stumps and logs may not be used for fill material unless approved by the Community Development Department. Excess material shall either be removed from the premises or leveled and covered with topsoil and seeded as hereinafter provided.
   (b)   If the proposed method of soil erosion control is by re vegetation, the specifications for the work shall provide that any layer of topsoil over the area to be excavated, graded or filled shall be set aside and retained on the premises in sufficient quantity to cover all surfaces which shall remain exposed, except rock, to a depth of at least four inches, with topsoil added if necessary to make up any deficiency. The specifications shall also provide that at the completion of re spreading of topsoil it shall immediately be harrowed or raked to establish a seedbed and shall be seeded for grass, permanent pasture mixture or other approved fast growing vegetation and shall be repeated as often as necessary until the area is stabilized.
   (c)   In the case of extended operations, except for access drives and the actual work area, the completed portion of the excavation, filling or grading operation shall be subject to the provisions of subsection (b) hereof and the operation shall be completed prior to the reissuance of the permit under Section 907.06(c).
   (d)   Where a permit has been issued for the excavation of a lake or pond, the provisions of this section applicable to seeding shall not apply to that part of the excavation below the water mark of such lake or pond.
   (e)   Property corners shall be set and property lines shall be marked before the commencement of the work and such markings shall be maintained through the duration of the work.
   (f)   The applicant shall notify the Community Development Department of the following, when and as completed:
(1)   Rough grading;
(2)   Final grading before seeding; and
      (3)   All re establishment and construction work. The Community Development Department, upon such notification, shall make field inspections on the site before rough grading, after final grading, before seeding and at the completion to determine if work in progress and the completed operation have been performed in accordance with this chapter.
   (g)   Upon completion of the work, where a permit is required, the owner or his/her authorized agent shall cause to be prepared by the project engineer or surveyor of record an "as built" drawing showing the elevations and contours actually established. The "as built" drawing shall be reviewed by the Development Engineer and approved as conforming to the approved plan prior to the release of the performance bond. (Ord. 1990-44. Passed 8-8-90; Ord. 1991-23. Passed 5-1-91.)