§ 153.035 WARRANTY/MAINTENANCE GUARANTEE.
   (A)   The subdivider shall submit either a warranty/maintenance bond or a letter of credit for an amount determined by the City Engineer.
   (B)   The required warranty period for materials and workmanship from the utility contractor installing public sewer and water mains shall be two years from the date of final written city acceptance of the work.
   (C)   The required warranty period for all work relating to street construction, including concrete curb and gutter, sidewalks and trails, materials and equipment shall be subject to one year from the date of final written acceptance, unless the wearing course is placed during the same construction season as the bituminous base course. In those instances, the subdivider shall guarantee all work, including street construction, concrete curb and gutter, sidewalks and trails, material and equipment for a period of two years from the date of final written city acceptance of the work.
   (D)   The required warranty period for trees and landscaping is one growing season following installation.
   (E)   The required warranty period for erosion control will be as established in the development agreement.
(Ord. 879, passed 10-28-2020)