§ 156.052 FINAL MAP.
   After the completion of the construction of the improvements, a master copy of a final map of the improvements accompanied by three prints shall be submitted to the Code Administrator. The master copy of the map shall be on heavy, transparent paper, Mylar or cloth in a form suitable for providing clear and legible prints or copies there from. The maps shall show the exact location and nature of utilities located under or along streets, alleys or easements. Valves, hydrants, ditches, catch basins, culverts, sewer lines and special fittings or feature shall be shown and located as they were installed and constructed.
(Ord. passed 10-14-2003; Ord. passed 11-10-2003; Ord. passed 11-14-2004; Ord. passed 9-11-2007)
§ 156.053 FINAL PLAT PROCEDURES.
   Final plat procedures are detailed in §§ 156.054 through 156.058.
(Ord. passed 10-14-2003; Ord. passed 11-10-2003; Ord. passed 11-14-2004; Ord. passed 9-11-2007)
§ 156.054 SUBMISSION OF FINAL PLAT FOR REVIEW.
   (A)   The final plat and six copies shall be filed with the Code Administrator along with a written request for approval. The final plat submitted shall include all plans and specifications and other such documents as may be necessary concerning the form of performance guarantee or bond to be used, if any.
   (B)   The Code Administrator shall review the material submitted to determine whether or not it is complete. If the material is incomplete, the Code Administrator shall return the final plat and accompanying documents to the applicant with a written description of what items are missing. Upon receipt of a complete final plat application, the Code Administrator shall forward one copy of the final plat to the County Engineer and the remaining material to the County Board.
(Ord. passed 10-14-2003; Ord. passed 11-10-2003; Ord. passed 11-14-2004; Ord. passed 9-11-2007)
§ 156.055 COUNTY ENGINEER REVIEW.
   The County Engineer and the Township Highway Commissioner shall review the copy of the final plat submitted to him or her by the Code Administrator and shall return any comments to the Code Administrator within 15 days of receipt.
(Ord. passed 10-14-2003; Ord. passed 11-10-2003; Ord. passed 11-14-2004; Ord. passed 9-11-2007)
§ 156.056 SUBDIVISION AND LAND USE REVIEW AND ACTION.
   (A)   The Code Administrator shall, upon receipt, forward any comments received from the County Engineer to the Subdivision and Land Use Committee.
      (1)   The Subdivision and Land Use Committee shall review the final plat and documentation and shall take action on the final plat within 90 days from the date on which the last required document or other supporting data was filed with the Code Administrator, unless such time is extended by mutual consent.
      (2)   The Code Administrator shall publish a notice of final plat for four weeks in a local newspaper of general circulation throughout the county. The Subdivision and Land Use Committee shall set forth the grounds for its recommendations and transmits them to the County Board for their consideration. The County Board, in turn, submits findings for non-approval or approval to the subdivider within said 90 days a written notice of such action to the applicant.
   (B)   The County Board shall not approve a final plat unless the following conditions are met:
      (1)   The final plat conforms to the preliminary plat approved previously;
      (2)   The final plat meets the design standards and engineering specifications set forth herein;
      (3)   The final plat meets all requirements of the laws of the state; and
      (4)   The subdivider or applicant agrees to post a performance guarantee or bond with the county equal to the estimated costs of all improvements to be dedicated to the county, township or any public body for maintenance and operation.
(Ord. passed 10-14-2003; Ord. passed 11-10-2003; Ord. passed 11-14-2004; Ord. passed 9-11-2007)
§ 156.057 SOIL AND WATER CONSERVATION DISTRICT REVIEW.
   The County Board may, if it believes that substantial changes have been made from the preliminary plat, request that the Soil and Water Conservation District review the final plat.
(Ord. passed 10-14-2003; Ord. passed 11-10-2003; Ord. passed 11-14-2004; Ord. passed 9-11-2007)