§ 36.015 BUILDING PERMIT FEES.
Min. Cost
Cost per Sq. Ft.
Min. Cost
Cost per Sq. Ft.
1.
Limited permits (100 sq. ft. and less than 1,250 sq. ft.)
$50
   Accessory buildings, pole barns, decks (over 25 sq. ft.)
(plus storm water and occupancy permit fees)
2.
Demolition permits
$50
3.
Limited permits (over 1,250 sq. ft.)
$50
$20.57 x 1.06 x 0.002
   Accessory buildings, pole barns
4.
Manufactured home permits
$50
$50 x 1.06 x 0.003
5.
Residential permits (180 days + 90-day extension)
$100
   New construction (living area minimum 400 sq. ft.)
$65.73 x 1.06 x 0.002
   Attached garage
$17.07 x 1.06 x 0.002
   Unattached garage
$20.57 x 1.06 x 0.002
   Unfinished basement
$12.23 x 1.06 x 0.002
   Finished basement
$18.80 x 1.06 x 0.002
   *2nd 90-day extension
half the cost of original permit fee
6.
Commercial permits (180 days + 90-day extension)
$100
cost x 1.06 x 0.003
   New construction, commercial development, additions
   *extension fee to be determined on project type
7.
Certificate of occupancy (residential and commercial)
$20
8.
Temporary occupancy permit (60 days)
$100
9.
Plan review fee
   Residential plan review
$50
   Commercial plan review
$100
10.
Signs and billboards
 
   Signs less than 249 sq. ft.
$30 for first 30 sq. ft. and $0.30 for each sq. ft. thereafter
   Billboard 250 sq. ft.—600 sq. ft.
$800 (each sign on same pole)
   Annual renewal permit fee for single side sign
$125
   Annual renewal permit fee for double side sign
$250
11.
Storm water management fee
sq. ft. x 0.04 residential
   Assessed on all buildings placed on permeable ground
sq. ft. 0.04 mobile home
 
project cost x 0.002 commercial
12.
Variance application fee
$2,000
13.
Additional inspections
$100
 
(Res. passed 4-9-2019; Ord. revised 2-21-2020; Ord. revised 10-15-2021; Ord. revised 8-8-2023)