Proposed or modified wind turbines shall meet the following design requirements:
(A) All above-ground components must be white, grey, or non-obstructive in color;
(B) Lighting shall be limited to FAA requirements;
(C) Signage shall be limited to appropriate warnings and turbine manufacturing/owner on nacelle;
(D) Power lines shall be buried; and
(E) Shall be considered abandoned after one year of no production. The owner shall have 90 days for removal after abandonment.
(Ord. passed 4-10-2017) Penalty, see § 150.999