§ 153.048 CERTIFICATES OF OCCUPANCY.
   (A)   Applicability. No structure or zoning lot or part thereof for which a zoning permit has been issued shall be used or occupied until the Building Official and/or the Zoning Administrator has, after final inspection, issued a certificate of occupancy indicating that the use or structure complies with all applicable requirements of the zoning permit and this chapter. This certificate of occupancy may be combined with or made a part of the certificate of occupancy required under the Building Code. The issuance of a certificate of occupancy shall not be construed as waiving any provision of this chapter or the applicable zoning permit.
   (B)   Utility connections.
      (1)   Electric or gas utility companies or cooperatives shall not provide their respective utility until receipt of an approved certificate of occupancy.
      (2)   Temporary electrical power permits shall require authorization from the Zoning Administrator prior to such services being provided by the utility companies.
      (3)   Temporary power poles shall require authorization from the Planning/Zoning Department and inspection by the building inspector and the utility before power is permitted to be turned on.
(Ord. 2012-06, § 3.9, passed 10-18-2012; Ord. 2012-21, passed 12-20-2012)